Weekly Schedule Update – April 27, 2012

Weekly Schedule Update
April 27, 2012

  • Phase 1 (2/20/2012 – 5/31/2012)
    • North Taylor St. started Monday, February 20, 2012
    • Sewer installation complete
    • Stormwater installation complete
    • Franchise utility installation complete
    • Work on sidewalk lids on the East side of North Taylor St.
      • Remaining gap in the new sidewalk finished in about 4 weeks (waiting for a freight hatch)
    • Work on sidewalk lids on the West side of North Taylor St.
      • Start 3/20/2012
      • Lid removal complete
      • Constructing footings in tunnels – complete
      • Installation of Structural Steel Beams – 4/17/2012 to 5/3/2012
      • Sidewalks finished 5/31/2012
    • Work on Washington Street/Taylor Street Intersection
      • Grading for subgrade complete
      • Pouring concrete crosswalks in late May
  • Phase 2 (3/6/2012 – 4/27/2012)
    • Sidewalks complete
    • Trees to be installed in June
  • Phase 3 (5/21/2012 – 6/15/2012)
    • Relites – chip off concrete/asphalt to expose relites is complete.
    • Lid removal at the Public House to start the week of 5/21/2012 or 5/28/2102
  • Phase 4 (3/12/2012 – 6/29/2012)
    • Franchise utility installation complete
    • Work on sidewalks/sidewalk lids
      • Lid removal complete
      • Remove at grade sidewalks complete
      • Buildup of the roadway retaining walls along Building 25 (Admiralty Apartments) and Building 40 (Surf Restaurant) started the week of 4/23/2012
      • Lid removal for the Hastings Building to start on Tuesday or Wednesday the week of 4/30/2012
      • Start grading to pour curbs – 4/25/2012
      • At grade sidewalks finished end of May
      • Wood decking finished in June
  • Utility Service Conversions
    • Utility providers will pull underground wires the week of 6/4/2012
    • Building services connected to underground utilities the week of 6/4/2012 and 6/11/2012