Weekly Schedule Update
March 23, 2012
- Phase 1 (2/20/2012 – 5/4/2012)
- North Taylor St. started Monday, February 20, 2012
- Sewer installation complete
- Stormwater installation on the North side of Taylor St. complete
- Franchise utility installation
- Start 2/28/2012
- Finish 4/3/2012
- Work on sidewalk lids on the East side of North Taylor St.
- Start 2/28/2012
- Pouring the concrete curb starting 3/26/2012
- Sidewalks finished 4/16/2012
- Work on sidewalk lids on the West side of North Taylor St.
- Start 3/20/2012
- Lid removal 3/22/2012 (starting at Washington St. and moving towards Water St.) – Individual doorway will be closed for 3-4 hours for removal of sidewalk and placement of temporary wooden bridges.
- Lehani’s, Kitsap Bank and Hanazono Asian Noodle Monday am.
- Baker Building Tuesday AM.
- Sidewalks finished 4/25/2012
- Work on Washington Street/Taylor Street intersection starting 3/26/2012
- Concrete pouring for half the intersection 3/29/2012
- Phase 2 (3/6/2012 – 3/22/2012)
- Sidewalks
- Pouring sidewalk next week (3/26 – 3/30)
- Sidewalks
- Phase 3
- Relites – chip off concrete/asphalt to expose relites (3/26-3/30)
- Phase 4 (3/12/2012 – 5/24/2012)
- Franchise utility installation
- Start 3/12/2012
- Finish 4/3/2012
- Work on sidewalks/sidewalk lids
- Continue Lid removal (both sides south end)
- Continue on grade sidewalk removal
- Sidewalks finished end of May
- Franchise utility installation