Weekly Schedule Update – March 23, 2012

Weekly Schedule Update
March 23, 2012

  • Phase 1 (2/20/2012 – 5/4/2012)
    • North Taylor St. started Monday, February 20, 2012
    • Sewer installation complete
    • Stormwater installation on the North side of Taylor St. complete
    • Franchise utility installation
      • Start 2/28/2012
      • Finish 4/3/2012
    • Work on sidewalk lids on the East side of North Taylor St.
      • Start 2/28/2012
      • Pouring the concrete curb starting 3/26/2012
      • Sidewalks finished 4/16/2012
    • Work on sidewalk lids on the West side of North Taylor St.
      • Start 3/20/2012
      • Lid removal 3/22/2012 (starting at Washington St. and moving towards Water St.) – Individual doorway will be closed for 3-4 hours for removal of sidewalk and placement of temporary wooden bridges.
        • Lehani’s, Kitsap Bank and Hanazono Asian Noodle Monday am.
        • Baker Building Tuesday AM.
      • Sidewalks finished 4/25/2012
    • Work on Washington Street/Taylor Street intersection starting 3/26/2012
      • Concrete pouring for half the intersection 3/29/2012
  • Phase 2 (3/6/2012 – 3/22/2012)
    • Sidewalks
      • Pouring sidewalk next week (3/26 – 3/30)
  • Phase 3
    • Relites – chip off concrete/asphalt to expose relites (3/26-3/30)
  • Phase 4 (3/12/2012 – 5/24/2012)
    • Franchise utility installation
      • Start 3/12/2012
      • Finish 4/3/2012
    • Work on sidewalks/sidewalk lids
      • Continue Lid removal (both sides south end)
      • Continue on grade sidewalk removal
      • Sidewalks finished end of May