Weekly Schedule Update – March 9, 2012

Weekly Schedule Update
March 9, 2012

South block of Taylor Street will be closed to vehicle traffic starting Monday, March 12th

Phase 1 (2/20/2012 – 5/4/2012)  - North Block of Taylor Street

  • Sewer installation (2/21 – 2/23)
    • Complete
  • Stormwater installation
    • Complete
  • Franchise Utility Installation
    • Started 2/28/2012
    • Finish 3/20/2012
  • Work on sidewalk lids on the East side of North Taylor St.
    • Started 2/28/2012
    • Finish 3/30/2012
  • Work on sidewalk lids on the West side of North Taylor St.
    • Concrete cutting starting 3/20/2012
    • Start 3/20/2012
    • Finish 4/18/2012

Phase 2 (3/6/2012 – 3/22/2012)  - Water Street North Side near Quincy

  • Concrete Cutting – complete
  • Lid Removal Starting – complete
    • Sidewalk construction
    • Started 3/6/2012
    • Finish 3/22/2012

Phase 4 (3/13/2012 – 5/24/2012) – South Block of Taylor Street

  • Franchise Utility Installation
    • Start 3/12/2012
    • Finish 3/20/2012
  • Stormwater installation
    • Start 3/12/2012
    • Finish 3/15/2012
  • Work on sidewalk lids – south end of the block
    • Concrete cutting starting 3/19/2012
    • Start 3/20/2012
    • Finish 5/22/2012