Weekly Schedule Update – 3/2/2012

Weekly Schedule Update
March 2, 2012

  • Phase 1 (2/20/2012 – 5/4/2012)
    • North Taylor St. started Monday, February 20, 2012
    • Sewer installation (2/21 – 2/23)
      • Complete
    • Stormwater installation on the North side of Taylor St. between Washington St. & Water St.
      • Complete
    • Franchise Utility Installation
      • Start 2/28/2012
      • Finish 3/20/2012
    • Work on sidewalk lids on the East side of North Taylor St.
      • Start 2/28/2012
      • Finish 3/30/2012
    • Work on sidewalk lids on the West side of North Taylor St.
      • Start 3/20/2012
      • Finish 4/18/2012
  • Phase 2 (3/6/2012 – 3/22/2012)
    • Concrete Cutting 3/6/2012
    • Lid Removal Starting 3/7/2012